Texte Wouter Polspoel | Photos Photos Pellikaan

In Hoeilaart, just before the construction industry’s summer break, Pellikaan completed the second and largest phase of work on the Koldam sports and youth complex. The project aimed to bring the outdated buildings up to current standards and was delivered on a design & build basis with the help of Architectengroep A4. The new and renovated buildings are characterised primarily by the use of concrete and steel, with particular attention paid to sustainability through water management and integration into the surroundings.

After the existing sports hall was renovated in 2018 as part of the first phase, with the building refurbished and extended to include a dojo, a clubhouse, a youth centre and additional changing rooms, work moved on to the second phase in May last year. “The municipality of Hoeilaart wanted the rest of the site, namely two football pitches and a tennis court, to undergo a major renovation to bring them up to current standards,” explains Stijn Biesemans, project manager at Pellikaan. “A new 10-metre-high sports hall was to be built next to the building we had completed in 2018, and the old football clubhouse was to make way for a shared clubhouse for football and tennis, over two floors, with players’ changing rooms on the ground floor. In addition, two tennis courts, two padel courts and two synthetic-turf football pitches, one slightly smaller than the other, were built in place of an existing full-size football pitch, along with a large car park. It was only later that it was decided to add several petanque courts as well. This was all right up our street, given that we specialise in delivering multi-purpose sports facilities.”

A context-sensitive design
The second phase of the transformation of the Koldam site was delivered under a Design and Build contract, with the architectural practice working for Pellikaan rather than directly for the municipality of Hoeilaart. Stijn Biesemans explains: “The practice was Architectengroep A4 from Leuven, with whom we had worked before. The architects designed the new sports hall and the tennis and football clubhouses as a concrete structure, clad at the lower level with concrete façade panels and at the upper level with black sandwich panels. The sports hall roof structure was built using timber beams, while the clubhouse roof structure is steel, which is clearly visible from the outdoor stand. The stand was built against the clubhouse and rests on steel columns, so it also serves as a covered bicycle shelter. We also installed the flooring there. The stand is designed not only for watching football matches, but also to offer a wide view across the whole site.”

“But that is not the only way the surroundings influenced the architects’ design. The entire site layout was brought up to current standards,” explains Stijn Biesemans. “That is why, in their landscape design, the architects placed crushed-stone infiltration crates just beneath the top finishing layer, to temporarily store rainwater and allow it to infiltrate into the ground. The gradients we created across the site also help direct rainwater towards the waterways.” “
This creates a good sense of cohesion between the building and its surroundings. “That is one of Pellikaan’s guiding principles,” says Stijn Biesemans. “Another measure that contributes to this is the installation of nets to stop tennis or footballs ending up in neighbours’ gardens, thereby avoiding conflicts.”

Final phase under way
A conventional gas boiler was chosen to heat the new buildings, but the roof of the new sports hall was designed to accommodate more solar panels than the hall needs for its electricity consumption. “The idea is that the surplus power generated can be used by the tennis and football clubhouse,” concludes Stijn Biesemans.
The renovated site has now been operational for several weeks. A skatepark and a green area are currently being developed as part of the third and final phase.